Project
The project consists in asphalting the road of the Bouna-Doropo-Burkina Faso border.
The road has a length of 91 km, a width of 7.00 m and two shoulders of 1.50 m width outside the towns and 2.00 m width within the towns.
Hydraulic works consist of:
- simple and multicellular culverts (up to 6 cells);
- bored gutter type;
- slab bridges with 4 spans of 20m are projected to cross the wadis, to drain run-off water and generally to put out of water the said road.
Our mission
- Contrôle et supervision des travaux